July 05
--------------------------------------------------------------------
LTM 1250 WITH LUFFING JIB
RIGGING NEW AC EQUIPMENT ON TO COLLAGE SPORTS FACILITY
IN BROOKLYN NY.
BOOMING UP
UNITS WEIGH 30000LBS
TIGHT SET UP
MAIN BOOM AT 75 DEGREES FOR FURTHEST PIECE
Rigging Large Chiller into Power plant
Ltm 1200 with 99kps ctw
Path into building was hollow so shoring was required
and plates used to protect the floor
Bringing the 1st section 78,000lbs using 2 forklifts and 15 ton cpty scates
2nd section 58,000lbs
sliding on to pad
Mating the 2 sections
LTM 1250 236' MAIN 104,000LBS CTW
RIGGING NEW CHILLER INTO BUILDING
1ST PIECE 10,000LBS
2ND PIECE 24000LBS
UNIT HAD TO BE PUT ON THEIR SIDE TO BE BROUGHT THROUGH LOW OPENING
3RD PIECE WEIGHED 22000LBS
TAG LINE FROM THE STREET LEVEL HELPED
CONTROL THE PIECE INTO THE OPENING
-----------------------------------------------------------------------------------------------------------
Leveling Ltm 1100 on major hill
crane had to be walked up on 2 x1' mats high
and 2 x1' mats high for the outriggers to level it out on this street